Project History
IPSCO Steel (Alabama) Inc.
 
230/34.5 kV MVA Main Substation, Design, Supply and Installation 
Design Build of 230/34.5 kV substation and components including
  
230 kV circuit switchers  
34.5 kV SF6 outdoor circuit breakers  
6.20 Mvar filters, mimic protection and control panels
  
Control building, foundation, overhead aluminum bus and structures  
Site grading, oil containment system, grounding and fencing

IPSCO STEEL (Alabama) Inc. Kvaerner Metals
 
Power Distribution Electrical   
Installation of all 34.5 kV cable feeders and terminations  
Installation of unit substations, transformers, switchgear, control components, and protection components, including oil filled and dry type transformers  
34.5 kV vacuum circuit breakers and disconnect switches, 34.5 kV 4160V and 480V distribtion components  
Custom bus installation

IPSCO Steel (Alabama) Inc. International Mill Service 
 
Scrap & Slag Facility   
Installation Hi-Mast Lighting and electrical track switches  
Installation of sight utilities  
Design and installation of custom underground cable duct banks  
Installation of control and distribution components 

IPSCO Steel (Alabama) Inc. Kvaerner Metals
 
Hi-Bay Lighting, Design, Supply & Installation  
Lighting design and installation of all high back lighint in the following areas  
Meltshop  
Caster  
Rolling Mill  
Plate Mill

IPSCO Steel (Alabama) Inc. Kvaerner Metals 
 
Electrical Installation Communications Phase 2
 
Installation and termination of plant telephone, fribre-optics, ethernet and commincations systems

ISPCO Tubulars Inc. Camanche, Iowa
Finishing & Testing Area Equipment Upgrades & Improvements 
Whip conveyor installation
 
Wire MCC 
Installation of HSS conveyor  
Fabrication and installation of HSS Control Station

 
 Ipsco Inc.
 
Ladle Metallurgical Furnace Transformer Installation  
Installation of 25MVA 15kV Ladle Metallurgical Furnace transformer feeding a twin LMF  
Installation and wiring power protection and control elements  
Installation, wiring and commissioning of alloy conveyance and weighing equipment

Caribbean Utilities Company
 
15 kV Cable Installation  
Detail design and installation of 15kV cable system in a utility substation  
Incorporation of 32 runs of 1500 feet through a complex underground ductbank system and 5 precast concrete manholes  
Development of installation procedures using custom sheave arrangements to install 3 single conductor concentric neutral cables in the underground ductank systems whule adhering to manufacture's specification on cable tensions and side wall pressure limits

IPSCO Inc. Transfer Industries
 
SpiralControl & Power System Upgrade  
Installation of all control and distribution components
Installation of 3 1500 kVA substations and 1 1000 kVA substation  
Renovations to a 10 MVA, 138/13.8kV substation  
Installation of AC variable speed drives  
Renovations to AC & DC welders to allow for remote PLC control and monitoring

IPSCO Inc.
 
24" Mill Installation - New constructor  
Installation of a 138/13.8kV 10 MVA substation and all associated cables  
Installation of 6 1500 kVA substations  
Installtion of 480V distribution switchgear

City of Regina
 
Water Treatment Facility  
Motor Control Installation  
Contril & Instrumental Design

IPSCO Tubulars Inc. Camanche, Iowa
Electical Installation of Hydro Modications 
Installation of hydro tester midifications  
Electrical installation of gangsaws 
Carribean Utilities Company Aea Brown Boveri
Installation of High Voltage Cable   
Installation of 69kV cables from transformers to 15kV swtichgear and generators complete with termination
  
Installation of 69kV cable from GIS switchgear to unit sub transformers complete with terminations

IPSCO Inc.
 
Static Var Compensator Installation   
Installtion and commissioning of all elements of a 15 mV, 70 Mvar SVC  
Design and installation of 15kV feeders using custom cable configurations tied to furnace buses

IPSCO Inc.
New High Speed Pipe Mill, Blytheville, Arkansas  
Wiring of automation equipment

IPSCO Inc.
LaminarFlow Upgrade   
Installation of 3 MVA Substation  
Installation of 4-400 hp A.C. Variable speed drives for low pressure, high volume water pumping system

IPSCO Inc.
Fast Tracked Upgrade of 50 MVA to 65 MVA Arc Furnace Transformer   
Co-ordination of All Electrical and Mechanical Services for Removal of 50 MVA Arc Furnace Transformer and Replacement with 65 MVA  
Oversee Fabrication and Installation of an Adapter Base  
Co-ordination of Installation of Components During 24 Hour Production Periods  
Design and install 15 kV cable system for new transformer

IMC-Kalium
 
15kV and 5kV Cable Installation  
Troubleshooting, Consulting and repair to existing faulted calbes  
Emergency Back-Up Generator Installation  
Design and Installation of Pneumatic Controls

IPSCO Inc.
 
Addition of 3-1600 HP Fan Motors 
Design and Installation of Cable and Control Components for Motors and Fans  
Mechanical Installation of Drop Boxes, Conveyors and Blastgates as well as Ducting

IPSCO Inc.
 
72kV Substation Renovation  
Installation and commissioning of 2-1600 hp 6.9kV Fan Motors  
Design and Installation of 3000 AMP Cable Feeder, Breaker, Protection Elements

IPSCO Inc.
24" ERW Mill 138kV Substation Construction  
In Charge of All civil work  
Site Grading  
Pile Foundations  
Soil Resistivity  
Fabrication of all Steel Structures  
Substation Erection  
Installation of aHigh Voltage CT's and PT's and Related Structures  
Installation of Transformer and Subsequent Testing  
Fabrication ans Installation of Control Builings and Equipment  
Imbedded Conduits and High Voltage Duct Banks

IPSCO Inc.
 
Finish Mill Expansion  
Istallation of new 6.9kV switchgear and associated cables  
Installation of a thrid 4500 hp dc mill motor and parallelling controls  
Installation of dc drives for motors up to 1500 hp  
Installation of PLC and control components  
Commissioning of all control and power components